Special Service - Temporary / New Construction

  • Please call our office for an appointment.
  • General foreman will give an estimate.
  • Once an estimate is provided - 50% of the total cost must be paid before work can start.
  • PMLD requires a copy of the building permit for all new structures.
  • It is the responsibility of the premise owner to notify the Town's Wire Inspector once electrical work is completed.
  • PMLD must be notified in writing by the Town Wiring Inspector before any new service will be energized.
  • Premise owner must pay the remaining bill in full and complete a service application.
  • Once all requirements for electric service are met and approved, the typical meter installation period is two to five business days depending upon the existing service backlog.

* Please note that all new meter sockets should have a meter bypass.*